Tuesday, October 12, 2010

Construction has started!

Last week the California Conservation Corps worked to fence out the project area and harvest willows and sycamores from the site before construction began. A large pool was dug by the CCCs and lined with plastic sheeting to provide the willow and sycamore poles with water until we are ready to plant them.  Last week limbing and removal of Avocado trees was also done along the access road to the project site.  This week Peter Lapidus Construction began working on the toe trench on the downstream end of the project site. Peter will make his way up stream filling in the toe trench with large rock and laying back the bank to a more gradual grade. Check back later this week for more photos and updates as construction continues.

CCC crew working to harvest and salvage willow poles that would be lost during project construction.
Willow and Sycamore poles staying wet until they can be planted.












Initial toe trench being dug at the downstream end of the project site.